Design
How Is Steel Formwork Designed for Concrete Casting?
What happens from the moment the element drawings arrive until the formwork is assembled on site: specification, engineering design, design for manufacturing, quantities and support — and why each stage shapes the next.
6 min read
Steel formwork is what gives concrete its shape. Concrete arrives as a fluid, and whether it ends up as a bridge beam, a tunnel wall or a precast element with precise geometry depends on the formwork it is cast into. The formwork has to hold the concrete during the pour, keep the geometry true until the concrete hardens, and come apart again without damaging the element.
That is why designing steel formwork doesn’t start at the manufacturer, and it doesn’t end when the drawings are done. It starts with questions about the element and the project, moves through engineering design and design for manufacturing, and follows the work all the way to casting on site. At AHM Formworks we have been designing and manufacturing steel formwork for concrete casting since 1985. In this article we break the process into stages and explain what happens at each one, and why.
It all starts with understanding the element
Before a single line is drawn, you need to understand exactly what is being cast. Formwork for a beam that repeats along a bridge is very different from formwork for a special element cast only once, even when the dimensions are similar. The first questions are almost always the same:
- What is the element’s geometry, and which parts of it are especially complex: slopes, curves, recesses or projections?
- How will the formwork be used: for a single pour, or repeatedly throughout the project?
- Where will the casting take place: on site, at a precast plant, or somewhere with limited space and access?
- What are the requirements for the concrete surface, openings, sleeves and items to be cast into the element?
The answers shape every decision that follows. Formwork that will be used many times has to be built so it can be stripped and reassembled easily, again and again. Formwork for an element cast on site has to suit the assembly and working conditions there, and the contractor’s sequence of work. When this information isn’t clear at the start, it usually surfaces later, and by then every change costs more.
From specification to engineering design
The first stage of the work process is specification. This is where all the information about the element and the project is gathered — drawings, requirements, site constraints and schedules — and where we define, together with the client, what the formwork needs to do. It is also the stage to ask the less comfortable questions: what happens if the drawings change, where exactly will the formwork stand, and who will assemble it?
Specification is followed by engineering design. Here the engineering team decides how the formwork will be built: which parts it is made of, how it is supported, how the parts connect to one another, and how it withstands the forces fresh concrete exerts on it during the pour. Fresh concrete is heavy and pushes against the sides of the formwork, and the formwork has to hold its shape, without shifting or deforming, until the concrete hardens.
Engineering design also deals with questions that are just as practical: how the formwork is opened after casting, in what order the parts are stripped, and how the element is released without damage. Formwork that holds the concrete well but is hard to strip will slow the work down on every casting cycle.
Good formwork isn’t measured only by how well it holds the concrete, but also by how easily it can be assembled, stripped and used again.
Design that works for manufacturing too
Sound engineering design is essential, but it isn’t enough. The formwork also has to be made, so engineering design is followed by a separate stage: design for manufacturing. This is where the design is translated into drawings and instructions the factory can work from, part by part.
Design for manufacturing asks different questions: how to divide the formwork into parts that can be manufactured, transported and lifted; where to place the connections so that assembly is simple and accurate; and which processing operations each part needs, such as drilling and punching. A decision that looks minor on the drawing, like where a connection sits, can decide whether assembly on site is straightforward or cumbersome.
When the same company both designs and manufactures, these questions come up during design rather than when the parts reach the factory floor. The designer knows how each part will be made, and the factory receives drawings that were prepared from the outset to be buildable.
Quantities, schedules and the work process
Alongside the design, bills of quantities and estimates are prepared as part of project planning. This stage helps bring together the components of the work and carry the project from design into manufacturing in an orderly way.
It’s worth remembering that the formwork is part of the schedule of the whole project. Casting can’t begin until the formwork is ready and assembled, so its delivery date directly affects the contractor and everyone whose work follows. The earlier and clearer the information, the easier it is to plan manufacturing so the formwork arrives on time.
Here is the complete work process, from the first question to the site:
- Specification
- Engineering design
- Design for manufacturing
- Bills of quantities and estimates
- Manufacturing
- Support through casting, assembly and delivery
What happens once the design is complete?
Once the design is approved, manufacturing begins. The parts are made according to the drawings, go through the processing operations specified for them, and are prepared for assembly. But the work doesn’t end when the formwork leaves the factory.
The final stage of the process is support through casting, assembly and delivery. On site, things sometimes come up that weren’t visible on the drawing: access conditions that have changed, a change in the work sequence, or a question from the crew assembling the formwork for the first time. Support at this stage helps make sure the formwork is assembled as designed and that the first pour goes as it should.
Why design the formwork as part of the whole project?
It’s easy to treat formwork as just another procurement item: order it, receive it, start casting. In practice, formwork is tied to almost everything else in the project — the element drawings, the construction method, the equipment on site and the schedule. A decision made in the formwork design affects the work on site, and a decision made on site affects the formwork.
This is especially true in infrastructure, bridge and tunnel projects. The elements are large, the geometry is complex, and the same formwork is often in use for a long period. When the formwork is designed with the whole project in mind, not just the individual element, the work on site is more predictable and there are fewer surprises.
The earlier the formwork designer is involved, the more room there is to weigh alternatives before they turn into costly changes.
Across more than 500 projects we have delivered in Israel, we have seen time and again how important it is to understand the element and the project conditions from the very start. If you have an element to cast or a project at the design stage, you can send us drawings or a description of the element, and we’ll review the project requirements together.